Customer Challenge
Lead time from existing vendors was 30+ weeks, but customer required DDP delivery in 24 weeks
- Contract Value: $0.3 Million USD
- Structure Quantity: 7
- Number of Designs: 7
Achievements
The entire delivery will be completed within 16 weeks from date of manufacturing clearance.
- Submission of Design documents, Fabrication/Assembly/BOM Drawing, PLS-Pole “.bak” files, cage assembly drawing: 3 weeks
- Customer Clearance on drawings: 4 weeks
- Manufacturing of the entire order: 1 weeks
- Sailing time from Indian port to Canadian port – 7 weeks
- From Canadian port to customer site – 1 week