Customer Challenge
Customer had many design changes but still requested delivery per their original schedule if possible.
- Contract Value: $1.1 Million USD
- Structure Quantity: 61
- Number of Designs: 4
Achievements
Delivery of all poles was achieved within 24 weeks after final design changes.
- Submission of Design documents, Fabrication/Assembly/BOM Drawing, PLS-Pole “.bak” files, cage assembly drawing: 3 weeks
- Customer Clearance on drawings: 2 weeks
- Manufacturing of the entire order: 4 weeks
- Sailing time from Indian port to Canadian port: 6 weeks
- From Canadian port to customer site: 1 week