CASE STUDY #4
Customer Challenge: Customer requested delivery of all structures ASAP to minimze winter construction.
Contract Value: $0.9 Million USD
Structure Quantity: 7
Number of Designs: 4
Achievements: Delivery of all A-frames was achieved within 19 weeks ARO.
- Submission of Design documents, Fabrication/Assembly/BOM Drawing, PLS-Pole “.bak” files, cage assembly drawing: 2 weeks
- Customer Clearance on drawings: 2 weeks
- Manufacturing of the entire order: 3 weeks
- Sailing time from Indian port to U.S. port: 6 weeks
- From U.S. port to customer site: 1 week