Customer Challenge: Customer had many design changes but still requested delivery per their original schedule if possible.
Contract Value: $1.1 Million USD
Structure Quantity: 61
Number of Designs: 4


Achievements: Delivery of all poles was achieved within 24 weeks after final design changes.

  • Submission of Design documents, Fabrication/Assembly/BOM Drawing, PLS-Pole “.bak” files, cage assembly drawing: 3 weeks
  • Customer Clearance on drawings: 2 weeks
  • Manufacturing of the entire order: 4 weeks
  • Sailing time from Indian port to Canadian port: 6 weeks
  • From Canadian port to customer site: 1 week
\