Customer Challenge: Lead time from existing vendors was 30+ weeks, but customer required DDP delivery in 24 weeks
Contract Value: $0.3 Million USD
Structure Quantity: 7
Number of Designs: 7


Achievements: The entire delivery will be completed within 16 weeks from date of manufacturing clearance.

  • Submission of Design documents, Fabrication/Assembly/BOM Drawing, PLS-Pole “.bak” files, cage assembly drawing: 3 weeks
  • Customer Clearance on drawings: 4 weeks
  • Manufacturing of the entire order: 1 weeks
  • Sailing time from Indian port to Canadian port – 7 weeks