CASE STUDY #1

Customer Challenge: DDP delivery with detailed designing required within 24 weeks
Contract Value: $4.5 Million USD
Structure Quantity: 150
Number of Designs: 20


Achievements: Delivery commenced at 20 weeks and was completed by 24 weeks.

  • Submission of Design documents Fabrication/Assembly/BOM Drawing, PLS-Pole “.bak” files, cage assembly drawing: 3 weeks
  • Customer Clearance on drawings: 4 weeks
  • Manufacturing of the entire order: 4 weeks
  • Sailing time from Indian port to U.S. port – 7 weeks