CASE STUDY #1
Customer Challenge: DDP delivery with detailed designing required within 24 weeks
Contract Value: $4.5 Million USD
Structure Quantity: 150
Number of Designs: 20
Achievements: Delivery commenced at 20 weeks and was completed by 24 weeks.
- Submission of Design documents Fabrication/Assembly/BOM Drawing, PLS-Pole “.bak” files, cage assembly drawing: 3 weeks
- Customer Clearance on drawings: 4 weeks
- Manufacturing of the entire order: 4 weeks
- Sailing time from Indian port to U.S. port – 7 weeks
- From U.S. port to customer site – 1 week